Wellington region maintenance programme

$
0
0

Information about roadworks in the Wellington-Kāpiti region

Well maintained roads are an important part of keeping people safe.  While we aim to do this work with as little disruption as possible, we know that roadworks can be inconvenient.  Thanks for your patience and understanding while we do this important work.

Please drive carefully through work sites and stick to the temporary speed limits.  If you’re driving around the Wellington region, roadworks on the state highway network may affect your travel plans.

Below is a quick outline of the major works planned for the coming week from 1811 September 2016 .  We’ll keep you posted on future works and have regular updates on local radio stations.

State Highway 1

Location

Type of work

Start date

LocationType of workStart date

Ngauranga Gorge
Lane closures to allow crews to repair the high friction surface at the top of the Gorge.

Resurfacing

Monday and Tuesday night

Te Horo Beach Road Intersection
Lane layout changes and a temporary speed limit for shoulder widening works.

Shoulder widening

Monday and Tuesday daytime

Churton Park
Lane closures for road surface repairs (mill and fills).

Mill and fill repairs

Tuesday night

Paekakariki Bridge
Traffic will be controlled by stop/go to allow crews to work on bridge joints.

Bridge joint repairs

Tuesday and Wednesday nights

Paraparaumu south of Kapiti lights
Lane closures during the day for dig outs.

Maintenance

Friday daytime

North of Waikanae
Traffic will be controlled by stop/go for resurfacing works (mill and fills).

Resurfacing

Thursday night

Otaki
Traffic will be controlled by stop/go for resurfacing works (mill and fills).

Resurfacing

Thursday night

Otaihanga and Waikanae Straights
Crews a rerepairing guardrails so a temporary speed limit will be in place.

Barrier repairs

Tuesday daytime

State Highway 2

Location

Type of work

Start date

Rimutaka Hill Road
Numerous work sites on the Rimutaka Hill Road all  week to enable work for guardrail and underslip repairs. Traffic will be controlled by stop/go for

Guardrail, underslip repairs

All week during the day

Rimutaka Hill Road
Traffic controlled by stop/go to allow crews to repair an electronic sign. 

Repair Electronic Warning Sign

Tuesday

State Highway 58

LocationType of workStart date

Haywards
Ongoing work by Lanes Flat for Transmission Gully.

 

Monday to Friday

NOTE: If bad weather should strike, work will be postponed to the next suitable night.

Peka PekaParaparaumu
Traffic controlled by stop/go to allow crews to work onDaytime lane closure in the Peka Peka tie-insouthbound direction for treee felling south of the new expressway.Paraparaumu traffic lights.

Expressway roadworksTree felling

Sunday to Thursday nights

Mana Esplanade
Major resurfacing works at night along Mana Esplanade.starting from the Plimmerton roundabout to the Z service station for the next few weeks. Traffic will be controlled by stop/go.  For further information:

Resurfacing

Sunday to Thursday nights

Coast Road
TrafficOn Sunday night southbound traffic will be controlled by stop/go for to allow crews to resurface sections of the road (milldrainage repairs and fillss).on Wendesday night northbound for guardrail and footpath repairs.  

ResurfacingDrainage clearing

Sunday and Monday nightsnight

Terrace Tunnel and Mt Victoria tunneltunnels
Closed Sunday night.   PleaseMonthly routine maintenance will require the tunnel to be closed overnight.  Please follow the signed detour.

Routine maintenance

Sunday nightMonday / Tuesday nights respectively

Pukerua BayTawa Interchange Underpass
Traffic will be controlled by stop / go to enable UFB tovegetation removal work.

Vegetation removal

Thursday night

Johnsonville southbound offramp
The southbound offramp from SH1 heading into Johnsonville will be installed.closed and detour in place.

UFB installationLighting pole replacement work

TuesdayWednesday and Thursday night

Kuku Bridge
Traffic will be controlled by stop / go to enable crews to work.

Dig outs

Thursday night

Te Horo (Old Red Shed café)
Contraflow and temporary speed limit for pavement / road surface repairs.

Pavement repairs

Monday to Friday

Paekakariki
Traffic controlled by stop/go for barrier repairs.

Barrier repairs

Tuesday and Wednesday nights

State Highway 2

LocationType of workStart date

Rimutaka Hill Road Bridge 6
Traffic will be controlled by stop/go for guardrail repairs.

Guardrail repairs

Wednesday and Thursday

Rimutaka Hill Road
Traffic controlled by stop/go to allow crews to repair an electronic sign. 

Repair Electronic Warning Sign

Monday and Tuesday

Te Marua to Kaitoke
Crews are clearing slips. Traffic will be controlled by stop/go while the work is underway.

Slip clearing

Tuesday

State Highway 58

LocationType of workStart date

Haywards
Lane/contraflows near Mt Cecil for bank hydroseeding.

Hydroseeding of bank

Monday and Tuesday

NOTE: If bad weather should strike, work will be postponed to the next suitable night.