Wellington region maintenance programme

$
0
0

Information about roadworks in the Wellington-Kāpiti region

Well maintained roads are an important part of keeping people safe.  While we aim to do this work with as little disruption as possible, we know that roadworks can be inconvenient.  Thanks for your patience and understanding while we do this important work.

Please drive carefully through work sites and stick to the temporary speed limits.  If you’re driving around the Wellington region, roadworks on the state highway network may affect your travel plans.

Below is a quick outline of the major works planned for the coming week from 6 November 2016 .  We’ll keep you posted on future works and have regular updates on local radio stations.

 

Updated Monday 7 November, 1.30pm
All paving works are cancelled tonight Monday 7 November because of forecast heavy rain.

 

State Highway 1

Location

Type of work

Start date

Patterson St (by the Mt Victoria tunnel)
Southbound lane closures with diversions in place.

Sewer works

Sunday to Thursday night

Calabar Road
Altered lane layout and temporary speed limit for UFB installation works.

UFB installation work

Tuesday to Friday daytime

Coast Road
Traffic will be controlled by stop/go for to allow crews to resurface sections of the road.

Resurfacing

Sunday to Wednesday night

Vivian Street
Lane closures and detours for resurfacing work including the Terrace tunnel being closed on Sunday night as part of the project.

Night closures - Wed 9Sun 6 Nov
Alternative routes - Wed 9 NovSun 6 Nov

Resurfacing and aftercare

Sunday to Thursday night

Terrace offramp
Lane closure so crews can replace a sewer main.

Sewer main works

Monday to Friday after 9:30am

Manakau
Traffic will be controlled by stop go for mill and fill repairs to the road surface.

Mill and fills

Wednesday night

State Highway 2

Location

Type of work

Start date

Ngauranga Offramp
Land and shoulder closures while crews work on the cycleway and offramp.

Cycleway works

Monday to Thursday

Kennedy Good Bridge to Owen Street
Lane closures for slip clearing works.

Slip clearance

Wednesday night

North of Hebden Crescent
Lane closures for mill and fill pavement repairs.

Mill and fills

Thursday night

Rimutaka Hill Road
Traffic will be controlled by stop/go rock face and drainage.

Maintenance and repairs

Sunday to Wednesday

Featherston
Traffic will be controlled by stop/go for pavement repairs near the intersection of SH2 and SH53.

Pavement repairs

Thursday

Carterton passing lanes
Traffic will be controlled by stop/go while crews chip seal the passing lane just south of Carterton.

Second coat seal chip sealing

Tuesday

Greytown - fruitstalls
Traffic will be controlled by stop/go while crews chip seal the highway just north of Greytown.

Second coat seal chip sealing

Wednesday

Opaki Overbridge
Traffic will be controlled by stop/go while crews chip seal the overbridge.

Chipsealing

Monday and Tuesday

Mikimiki
Traffic will be controlled by stop/go while crews do repair and maintenance work.

Dig outs and stabilisation

Monday to Friday

State Highway 58

Location

Type of work

Start date

Postgate Drive roundabout
Traffic will be controlled by stop go to allow crews to do mill and fill pavement repairs.

Mill and fills

Monday and Tuesday night

Haywards – Mt Cecil to Paremata
Traffic will be controlled by stop/go while crews clear drains and slips at various locations.

Drainage and slip repair work

Thursday night

Haywards
Ongoing work by Lanes Flat for Transmission Gully.

 Construction

Monday to Friday

NOTE: If bad weather should strike, work will be postponed to the next suitable night.